Date: Phase I completed April 2024 & Phase II expected completion Summer 2025 | Owner: Cobb County School District | Size: 22,500 SF
Services Provided: Full Architectural, Engineering, Interior Design Services
Construction of an overhead and grade level walkways between buildings 5012 and 5080. Improvements made to designated STEM and CTAE classrooms: replace lighting with LED fixtures and ceiling tile; patch and paint walls; replace millwork and include vent hoods, gas valves, and sinks; and replace carpet with VCT. Scope for each classroom/space will be assessed on a case by case basis. Tennis courts converted into 98 parking spaces.